The Lekki Estates Residents and Stakeholders Association in conjunction with Eti-Osa Local Government have announced that there will be traffic diversion at Victoria Garden City intersection of Lekki-Epe Expressway, to aid reconstruction of the defunct intersection

In a notice made available to The PUNCH on Saturday, the diversion is expected to commence on Monday, October 24, 2022 and will last for four weeks.

The traffic diversion would mean that all movements on the three straight lanes will now be on the lane inwards Ajah.

It was gathered that the decision for the diversion was announced in a meeting after extensive deliberations with stakeholders about the status of the ongoing road/bridge construction, to also get their concurrence on the reconstruction of the intersection opposite VGC.

Adding that the planned exercise is expected to be carried out with “minimal inconvenience to commuters, if all parties cooperate with the project team and behave responsibly around the construction site.”

The statement read, “The overhead bridge is designed to have its landing point around the former intersection opposite VGC. The next phase of the project is to reconstruct the portion of road within that area.

“The sequence is as follows; Create a traffic diversion of the three straight lanes to the lanes meant for the bridge landing. All movements will now be on the lane inwards Ajah; remove all the asphalt surfacing and fill/raise the level of the road and lastly, reconstruct the now raised road.